In Bangladesh UN agency Goodwill Ambassador Kristin Davis urges action for Rohingya

“For me, the most shocking part of the Rohingya refugee crisis is the number of children who have had to flee their homes,” Ms. Davis, Goodwill Ambassador for the Office of the UN High Commissioner for Refugees (UNHCR), said at the end of her visit to Kutupalong Refugee camp in Bangladesh. “Over half of the refugees in the camp are children. Some of them have lost one or both parents and they are on their own,” she added. She said that they need everything, including the very basics of shelter, water and food. “I can’t imagine going through what these children and their families have gone through, much less having the strength, resilience and extraordinary bravery these children possess,” she said. According to UNHCR, the Rohingya are a stateless minority in Myanmar. Since violence erupted on 25 August 2017 in Myanmar’s northern Rakhine state, more than 600,000 people have fled to Bangladesh. Children make up 54 per cent of the total population. A recent survey of more than 170,000 families, or 740,000 individuals found that 5,677, or 3.3 per cent, of the households are headed by children; more than 4,800 households, or 2.8 per cent, include separated and unaccompanied children; and as many as 14 per cent of families are composed of single mothers holding their families together with little support in harsh camp conditions. “This is currently the fastest growing refugee crisis in the world and seeing the impact of this emergency on children is devastating,” Ms. Davis continued. UNHCR requires $83.7 million to respond to humanitarian needs in Bangladesh until the end of February 2018 in order to meet the acute needs of children, women and men fleeing conflict. UNHCR’s response is currently less than half funded. “The fact is that more funding, more donations, will save lives. Governments, the public, private sector, businesses, we all need to do what we can to help and donate now to support the Rohingya refugees,” Mr. Davis added. read more

Lundin Gold Fruta del Norte soft tunnelling completed development now in hard

first_imgLundin Gold Inc is pleased to announce that soft tunneling was completed in December 2017 and mine development is now into hard rock at its Fruta del Norte gold project in Ecuador. “Tunneling through soft clay was a significant risk factor to underground mine development due to the potential for ground failure. We were able to get through this challenging task, and the mine development is now advancing at a quicker pace,” said Ron Hochstein, President and CEO of Lundin Gold. “We are also ramping up other major projects, including the process plant and powerline.”The company transitioned from soft tunneling to hard rock tunneling in December 2017, working through 77 m of saprolite (soft clay) in the first decline and 69 m in the second. Drilling and blasting in hard rock commenced on December 7th in the first decline and December 17th in the second, and currently the advance in hard rock reached 100 m and 78 m, in the first and second declines, respectively.In October 2017, Lundin Gold awarded the long-lead time grinding equipment packages, including the SAG and ball mills (complete with motors) and the flotation and filtration packages to Outotec Chile SA. The gravity mill, CIL and detox tanks, and ADR plant and gold room packages were recently awarded to FLSmidth USA Inc. TelSmith Inc. will provide the crushing packages for both the process plant and aggregate quarry crushers. ABB Inc has been awarded switchgear and substation equipment and transformers packages.Most of the mobile mine equipment orders have been placed. Importadora Industrial Agricola SA/Caterpillar will provide the underground mine scooptrams and trucks, as well as the surface earthworks and quarry equipment. Orders for the mine jumbos and bolters are expected to be awarded this quarter.The EIA for the powerline received final approval at the end of 2017. Easement agreements have been reached with 91% of affected landholders, and the Company expects the remaining easements to be obtained this quarter. Detailed engineering and procurement is well underway, and the engineering, procurement and construction contractor is on track to begin building the powerline this quarter.Regardless of difficult ground conditions, site earthworks are on schedule. Earthworks on the process plant is 13% complete with concrete mill foundations planned to start this quarter.The North Access Road is progressing well, and 32% of the road has been built. A second earthworks contractor was mobilised at El Pindal, where the North Access Road will link to the national highway system. Approximately 6 km needs to be built to connect the North Access Road from either side.All other construction disciplines are actively working on the 1,000-person construction camp which is nearing completion, with over 60% of the units currently available for occupancy. Combined with the existing camp, there are more than 1,200 beds available. During the last month, approximately 800 people were at site, including contractors.last_img read more