USC vs. Washington Game Time, Channel, Spread, Announcers

first_img Here’s all the details for Saturday’s contest:Game Time: 3:30 p.m. ETChannel: FOXSpread: Washington -10.5Over/Under: 61.5Announcers: Joe Davis, Brock Huard, Bruce FeldmanThe spread has the Huskies as a pretty big favorite in this one. It’s difficult to argue against UW. Not only is USC on the road, the Trojans are hot-and-cold. They might play well this weekend. But Washington, behind its home crowd, will be up for the challenge.Washington and USC kicks off at 3:30 p.m. ET on FOX. General view of Husky Stadium.SEATTLE, WA – NOVEMBER 19: A general view prior to the game between the Washington Huskies and the Arizona State Sun Devils on November 19, 2016 at Husky Stadium in Seattle, Washington. (Photo by Otto Greule Jr/Getty Images)A major Pac-12 showdown is happening this Saturday in Seattle. No. 17 Washington hosts No. 21 USC at Husky Stadium. Both teams are battling to win their divisions. Saturday is expected to be an offensive shootout.Washington already has a conference loss this season. So the Huskies are looking for their first conference win. UW’s offense has improved significantly this season. Quarterback Jacob Eason is one of the best offensive players in the Pac-12. He’ll go head-to-head with USC QB Matt Fink.The Trojans pulled off a shocking upset of Utah last Friday. They even did it without Kedon Slovis — who will miss this Saturday’s game. But Fink was phenomenal against the Utes, relying on USC’s talented receivers.Husky Stadium will be rocking with USC in town. Can Fink and the Trojans overcome the raucous crowd?last_img read more

Lundin Gold Fruta del Norte soft tunnelling completed development now in hard

first_imgLundin Gold Inc is pleased to announce that soft tunneling was completed in December 2017 and mine development is now into hard rock at its Fruta del Norte gold project in Ecuador. “Tunneling through soft clay was a significant risk factor to underground mine development due to the potential for ground failure. We were able to get through this challenging task, and the mine development is now advancing at a quicker pace,” said Ron Hochstein, President and CEO of Lundin Gold. “We are also ramping up other major projects, including the process plant and powerline.”The company transitioned from soft tunneling to hard rock tunneling in December 2017, working through 77 m of saprolite (soft clay) in the first decline and 69 m in the second. Drilling and blasting in hard rock commenced on December 7th in the first decline and December 17th in the second, and currently the advance in hard rock reached 100 m and 78 m, in the first and second declines, respectively.In October 2017, Lundin Gold awarded the long-lead time grinding equipment packages, including the SAG and ball mills (complete with motors) and the flotation and filtration packages to Outotec Chile SA. The gravity mill, CIL and detox tanks, and ADR plant and gold room packages were recently awarded to FLSmidth USA Inc. TelSmith Inc. will provide the crushing packages for both the process plant and aggregate quarry crushers. ABB Inc has been awarded switchgear and substation equipment and transformers packages.Most of the mobile mine equipment orders have been placed. Importadora Industrial Agricola SA/Caterpillar will provide the underground mine scooptrams and trucks, as well as the surface earthworks and quarry equipment. Orders for the mine jumbos and bolters are expected to be awarded this quarter.The EIA for the powerline received final approval at the end of 2017. Easement agreements have been reached with 91% of affected landholders, and the Company expects the remaining easements to be obtained this quarter. Detailed engineering and procurement is well underway, and the engineering, procurement and construction contractor is on track to begin building the powerline this quarter.Regardless of difficult ground conditions, site earthworks are on schedule. Earthworks on the process plant is 13% complete with concrete mill foundations planned to start this quarter.The North Access Road is progressing well, and 32% of the road has been built. A second earthworks contractor was mobilised at El Pindal, where the North Access Road will link to the national highway system. Approximately 6 km needs to be built to connect the North Access Road from either side.All other construction disciplines are actively working on the 1,000-person construction camp which is nearing completion, with over 60% of the units currently available for occupancy. Combined with the existing camp, there are more than 1,200 beds available. During the last month, approximately 800 people were at site, including contractors.last_img read more